The Roadworks have been completed early!

Things are back to normal from Sunday 22nd August.

PRESTON CROSSROADS carriageway is due to be resurfaced as part of a programme of road improvement works in the East Riding.

Work is scheduled to take place on five Sundays (weather permitting) on the following dates:

  • Sundays 18th, 25th July 2010
  • Sundays 8th, 15th and 22nd August 2010.

The work will be carried out on Sundays to minimise disruption to Heavy Goods Vehicles, public and school transport, commuter traffic and residents.

The improvement work will consist of replacing defective/worn ironwork, replacing up to 180 mm deep of existing carriageway surface, some isolated kerbing and a micro asphalt surfacing to footpaths. This will be completed by the reinstatement of road markings and traffic signal loops.

Due to the restricted width of the road and to undertake the work safely, it will be necessary to close the crossroads to all traffic (except emergency services) during working hours. Working hours will be 8am to 8pm. The council is asking residents living within the scheme limits to park vehicles away from the work area during working hours. Access will be via the roads approaching the crossroads. Pedestrians will have access at all times.

During the closure, traffic will be diverted via Saltend, Thorngumbald, Burstwick, Daisy Hill, Lelley and the B1239 near Sandyhill Nursery.

The normal Sunday bus services 78 and 277 will be changed on closure dates with revised arrangements made by east Yorkshire Motor Services (see EYMS Service Information).

For further information, please contact Mark Waterson, assistant principal engineer, on 01482 395637.

2 thoughts on “Preston Crossroads Road Improvements

  1. Good news! The Preston Crossroads roadworks have finished early, therefore Services 78 & 277 are able to return to their normal Sunday timetables from 22 August. The last date the alternative timetables operated was Sunday 15 August. On Sunday 22 August the normal timetables will be in place again.

  2. Services 78 & 277 – Preston crossroads.

    There will be special timetables in place for Services 78 & 277 every Sunday from 18 July until 22 August due to the roadworks at Preston Crossroads. The services will be unable to link Hedon and Sproatley as they normally do, and there will be some changes to bus times.

    These revised timetables will only be in operation on Sundays. For further details please ring BusCall Tel: 01482 22 22 22.

Leave a comment. You need to leave your FULL NAME.

Previous post Hedon Aerodrome iconic image
Next post Hedon Youth Club

Discover more from Hedon Blog

Subscribe now to keep reading and get access to the full archive.

Continue reading